Replacement of the long-distance transport pipeline at the Power Plant

Description

Pipes with diameters of 250 to 350 mm and a total length of about 800 m were replaced. The route led from the B6 production unit up to the fly ash storage. Assembly work consisted of:

  • Dismantling of existing pipelines
  • Repair of fix points and sliding points
  • Installation of new piping including new expansion joints and clamps
  • Pressure test

All work was carried out from work platforms and using cranes. Preparatory work (welding of flanges, preparation of bevels, etc.) is then carried out at the ground-level workplace. The key point of the whole project was the  dismantling and assembly of the 40 m long pipeline across the railway line, where the railway shutdown 24 hours only.

Year of implementation
05/2022 – 07/2022
Locality
Pocerady Power Plant, Czech Republic
> 30 years successful on the market
> 30 years
successful on the market
> 50 countries, where to find our work
> 50 countries,
where to find our work
Certificates for all production
Certificates
for all production
Comprehensive services from design to assembly
Comprehensive services
from design to assembly
Top